Warrego Highway Sewer Crossing

Client: Tunnel Boring Australia

Timeline: June 2016 - September 2016

RELATED PROJECTS

Civil Construction

Civil & Street Lighting Works - Coles Benowa U Turn

Civil Construction

Olsen Avenue Water Main

Pipejacking / Civil Construction

Micro Tunnelling Bardsley Avenue, Greenslopes

Civil Construction

Homework Caltex Civil Works

Boring of low pressure sewer main under existing 1500 diam stormwater drainage pipes & connection into manhole. Excavate jacking pit (9.5m long by 2.4m wide) with concrete floor and benching. Form up, supply & install launch pad/thrust wall in jacking pit. Supply & install of DN250 PE100 PN8 pipe; Construction of 2 x new manholes including PE lining. Open trench 16.73m; Reinstate carpark and asphalt, testing of sewer main including CCTV.