Construction of Manhole Chambers & Associated Drainage Works at Balfour Street, Darra - Stage 1
Client: Brisbane City Council
Timeline: September 2018 - March 2019
RELATED PROJECTS
Civil Construction
Civil & Street Lighting Works - Coles Benowa U Turn
Civil Construction
Olsen Avenue Water Main
Pipejacking / Civil Construction
Micro Tunnelling Bardsley Avenue, Greenslopes
Civil Construction
Homework Caltex Civil Works
Construction of 160m of reinforced concrete stormwater pipeline, diameters ranging from 375mm to 1500mm; supply and lay 25m 1800x1200 RCBC; construction of 12 new gullies including demolition of existing; construction of new lintels including demolition of existing; construction of 5 new manhole chambers including demolition of existing; replace 25m section of DN225 sewer main under stormwater trench.